Thailand · Warehouse
物流仓库 12,000㎡
为泰国消费品集团在曼谷港附近建造的配送中心,62 天完工,含两座夹层办公区。
- 所在地
- Thailand
- 完工时间
- 2024
- 建筑面积
- 12,000 m²
- 跨度
- 32 m
- 用钢量
- 780 t
The client needed a cross-dock distribution center within 90 days of groundbreaking. We engineered 32 m clear-span rigid frames with 8 m eave height, 12 dock levelers and a 1,200 m² mezzanine office block, then shipped 780 t of fabricated steel in nine 40'HC containers.
Our six-person erection supervision team worked alongside local crews, completing the frame in 38 days and full handover — cladding, doors, floors and offices — on day 62.